Government Incentives for Infrastructure Development

India is emerging to become a global leader in investing in world-class infrastructure projects, in view of concrete plans set out in the 2021 Budget. With unwavering growth in the Indian stock market witnessed by indexes touching unprecedented highs, the Indian infrastructure sector is filled with signs of optimism as the country reels out from the effects of the pandemic. Current trends suggest a boost in infrastructure spending that shall also facilitate infusion of overseas capita for investments in other sectors and an availability of credit for infrastructure projects.

The government’s National Infrastructure Plan for 2019 to 2025 has already supported more than 9000 projects having a total project cost surpassing USD 1949 billion.[1] The National Infrastructure Pipeline is a live database of infrastructure projects and provides attractive investment opportunities in projects worth more than INR 100 crores in sectors including Transport, Logistics, Energy, Water and Sanitation, Communication, Social and Commercial Infrastructure.[2]

 

Apart from this, opportunities are available through the government’s ‘India Investment Grid’ (IIG) for investing in stressed assets to allow the purchase of viable stressed assets which have the potential for being turned around.[3] IIG also facilitates Corporate Social Responsibility opportunities for businesses to invest in infrastructure building in the education, healthcare sectors and for poverty alleviation as part of their CSR spending.[4]

These investment opportunities are coupled with a bold move towards introducing National Bank for Financing Infrastructure and Development Act, 2021. The long-overdue initiative establishes a government-owned Development Finance Institution (DFI) for extending long-term affordable debt financing to infrastructure projects. The DFI is set to receive initial funding from the government and is projected to have a lending capability of a minimum of INR 5 trillion by 2024-25. The appointment of the veteran banker, Mr. K V Kamath as the chairperson of the newly set up INR 20,000 crore DFI- National Bank for Financing Infrastructure and Development, falls in alignment with the developmental and financial objectives of DFI.

The INR 40, 000 crore National Investment and Infrastructure Fund (NIIF) anchored by the Government of India in 2015 is also gaining momentum through its funds namely, Master Fund, Fund of Funds and Strategic Opportunities Fund each with a designated purpose.

 

Impetus has been given to the domestic manufacturing ecosystem through the Atmanirbhar Bharat initiative, especially to Micro, Small and Medium Enterprises (MSMEs) aiming to facilitate local manufacturing. As a further boost to the initiative, the government intends to achieve a turnover of US$ 25 billion including export of US$ 5 billion in aerospace and defense goods and services by 2025[5]. An increase in the capital expenditure will augment the procurement of weapons, aircraft, warships, and other military hardware. Posing as a lucrative market for defense companies, India gives orders worth US$ 100 billion a year for defense procurement.[6] Therefore, the Finance Ministry has permitted Foreign Direct Investment (FDI) in the defense for sector up to 74 percent under the automatic route leading to access of modern technology, strategic partnerships between foreign manufactures and defense equipment manufacturers in India. It also promotes active utilization of the Technology of Funds scheme that supports MSMEs in catering to the requirements of technological development in the defense sector.  

 

With a capital infusion of INR 1,000 crores to Solar Energy Corporation of India, there is a likely surge in large-scale solar installations, grid-connected projects, solar plants, and solar parks along with a phased manufacturing plan for solar cells, solar panels, and domestic production of solar inverters and solar lanterns.

 

The Government of India has also earmarked areas including highways, railways, power grids, and airports to monetize public infrastructure for financing new public projects. Statutory authorities have already begun setting up infrastructure investment trusts (InvIT) which will hold the public infrastructure assets for national as well as international institutional investors. Another avenue under consideration for obtaining public investment into infrastructure projects is issuance of tax-efficient zero-coupon bonds by infrastructure debt funds.

 

Major tenders worth more than INR 20 billion are expected to be issued in the coming financial year for public-private partnership in the management and operations of ports.

 

The logistics sector serves national trade, international trade, MSMEs, and start-ups. The launch of INR 100 crore Gati Shakti National Master Plan for Multi-Modal Connectivity has heralded new possibilities. This digital platform will incorporate the infrastructure schemes of various Ministries and State Governments like Bharatmala, Sagarmala, inland waterways, dry/land ports, UDAN etc; Economic Zones like textile clusters, pharmaceutical clusters, defense corridors, electronic parks, industrial corridors, fishing clusters, Agri zones will be covered to improve connectivity and make Indian businesses more competitive[7]. The National Logistics Policy is expected to promote seamless movement of goods through a focus on digitization, process re-engineering, multi-modal transport, EXIM trade, etc.[8] It is designed to streamline rules and address supply-side constraints, leading to lower logistics costs, the boost of trade, enhancement of Logistics Performance Index and greater competitiveness for Indian products worldwide.

 

In the power sector, apart from an INR 3 trillion outlay planned over the coming five years for revamping the power distribution scheme by providing distribution companies with financial assistance for developing a smart-metering infrastructure, the government is also in the advanced stages of launching a National Hydrogen Mission which may provide an opportunity for corporations in the power sector to engage in the export of green hydrogen and green ammonia while also meeting the domestic demand.

 

These dynamic initiatives clubbed with the use of India’s IT capabilities by creating monitoring mechanisms such as a dashboard to track the progress of publicly monetized infrastructure projects have created attractive opportunities for infrastructure companies to mobilize their assets into the establishment of new development projects.

 

Fox Mandal’s Infrastructure, Project Finance, and Energy Teams deliver unmatched expert services in wide-ranging areas of public infrastructure, inclusive of but not limited to ; transaction assistance for infrastructure projects, services of review, compliance, submitting tender documents, structuring and reviewing concession agreements, incorporation of Special Purpose Vehicles (SPVs), procuring relevant licenses and approvals, regulatory clearance facilitation, dispute resolution, strategy planning, and infrastructure contract bidding management.

 

As a commendation for the services rendered by Fox Mandal, the Firm featured in 2021 Legal 500 Rankings for its Projects & Energy Practice vertical.  

 

References: 

[1] https://indiainvestmentgrid.gov.in/national-infrastructure-pipeline

[2] https://indiainvestmentgrid.gov.in/opportunities/nip-projects/transport and https://indiainvestmentgrid.gov.in/national-infrastructure-pipeline

[3] https://indiainvestmentgrid.gov.in/opportunities/stressed-assets/transport?subSector=112%2C37%2C110%2C108%2C109%2C107%2C106%2C111%2C113

[4] https://indiainvestmentgrid.gov.in/opportunities/csr-projects?sector=29%2C10&subSector=97%2C99%2C157%2C94%2C100%2C93%2C102%2C105%2C96%2C95%2C103%2C104%2C98%2C112%2C37%2C110%2C108%2C109%2C107%2C106%2C111%2C113

[5] https://www.investindia.gov.in/sector/defence-manufacturing

[6] https://www.business-standard.com/article/economy-policy/higher-fdi-in-defence-sector-to-attract-mncs-give-make-in-india-a-boost-120051900698_1.html

[7] https://pib.gov.in/PressReleaseIframePage.aspx?PRID=1763638

[8] https://www.thehindubusinessline.com/opinion/logistics-and-supply-chain-trends-for-2021/article36366467.ece

 

Image Credits: 

Photo by David Rodrigo on Unsplash

These dynamic initiatives clubbed with the use of India’s IT capabilities by creating monitoring mechanisms such as a dashboard to track the progress of publicly monetized infrastructure projects have created attractive opportunities for infrastructure companies to mobilize their assets into the establishment of new development projects.

POST A COMMENT

Project Cost in Infrastructure Projects: Concept, Challenges and Way Forward

The IMF and Central Statistic Organization had dubbed the Indian economy as the fastest growing economy back in 2019. Moving forward, in 2021 despite the havoc wrecked by the pandemic on advanced economies across the globe, the IMF has kept India’s growth forecast unchanged at 9.5%. In order to sustain India’s growth momentum, the development of country’s infrastructure sector is cogent. The National Infrastructure Pipeline has been the focus of current policies, with an unprecedented increase in capital expenditure allocation for FY 2021-22 by 34.5% to INR 5.5 lakh crore to propel infrastructure creation. However, the April-June 2021 report of The Ministry of Statistics states that 470 projects sanctioned by the centre suffered from a cost overrun of 61.5 percent, that is Rs 4,46,169.37 crore[1].

Project cost remains the central concern for any seminal discussion on infrastructural projects in India or around the world. This is the nebulous point where a host of stakeholders would converge to dispute, disagree, or litigate. This article aims to discuss the concept of project cost and its various implications for the different stakeholders involved.

Introduction to Infrastructure and Projects

 

Costs that are reasonably incurred for the acquisition and construction of infrastructure are referred to as infrastructure costs. Hence, Project cost could mean the total cost of an infrastructure project.  In India, there is no clear definition of the term infrastructure. However, on 1st March 2012, the Cabinet Committee on Infrastructure approved the framework to include a harmonised master list of sub-sectors to guide all the agencies responsible for supporting infrastructure in India. These sub-sectors include transports and logistics, energy, water and sanitation, communication, and social infrastructure. Out of the plethora of these sub-sectors, during the fiscals of 2020-2025, it is expected that sub-sectors such as Energy (24%), Roads (19%), Railways (13%) and Urban (16%) shall constitute 70%of the projected capital expenditure in infrastructure in India[2]. The total capital expenditure as per the report is expected to be 102 lakh crore Indian rupees. Furthermore, in India, the current investment in infrastructure is USD 3.9 Trillion, and the required investment is USD 4.5 Trillion, leaving a gap of USD 526 Billion[3]. Therefore, the energy and infrastructure sector are instrumental in generating tremendous employment opportunities and drive a substantial increase in GDP per annum in India as well as countries all over the world.

 

Structure of Project Finance Transactions

 

The main parties involved in a project finance transaction structure are (i) The Authority or the Government (ii) The Private Party Investors/Developers, Sponsors or Promotors and (iii) the Lenders. These three parties are key players responsible for the determination of project costs in infrastructure and construction projects. The principal point of convergence for these three players is the project company (i.e., also known as special purpose vehicle) set up by the private party investors under which the infrastructure project is formed and under which the project exists in the concession agreement. The project cost is mainly estimated by the private party and the lenders who would finance in the form of equity and debt. The typical financial structure for infrastructure projects has a debt-to-equity ratio of 75:25. However, the ratio may vary depending upon the risks involved.

                Illustration I: Key parties that influence the project cost of an infrastructure project

                                                                                                                     

 

Risks that affect the Determination of Project Cost

 

Every project has certain risks attached to its completion. These risks influence the determination of project costs by the authority, the private parties and the lenders. The risks, in turn, then affect the total cost of the project. The risks affecting the three parties are explained below:

 

                                Illustration II: Risks that affect the determination of project cost

    

 Risk for Authority

Risk for Private Party
Investors

Risk for Lender

Technical or physical risks

Economic or market risks

Economic or market risks

Risk relating to land acquisition

Construction and completion risk – cost overrun/time
overrun/delays

Financing risks

For eg. Technical or physical risks may include risks
associated with
technology during
construction and operation as well as social and environmental risks.

For eg. Economic or
market risks may include input and output price variations, variation in
demand, debt/equity financing as well as counterparty risks.

For eg. Economic or
market risks may include input and output price variations, variation in
demand, debt/equity financing as well as counterparty risks.

The other risks that affect the cost of the project are contractual and legal risks, resource and raw material availability risks, demand risks, design risks, force majeure, property damage, permits, licenses, authorization, supply risk, social and environmental risks.

 

The Major Risks affecting Project Cost in India: Cost Overrun and Time Overrun

 

Out of the myriad of risks affecting project cost, the major risks in India are the risks associated with cost and time overruns. As many as 525 infrastructure projects were hit by time overruns, and as many as 470 infrastructure projects, each worth Rs 150 crore or more, were hit by cost overruns of over Rs 4.38 Trillion owing to delays, according to a report by the Ministry of Statistics, cited previously[4] The main causes for time overruns are delay in obtaining forest and environmental clearances, delay in land acquisition,  and lack of infrastructure support.  As per the report, there are other reasons like delay in project financing, delay in finalisation of detailed engineering, alteration in scope, delay in ordering and equipment supply, law, geological issues, contractual complications and delay in tendering.

 

The Key Elements of Project Cost

 

The elements of ‘costing’ include variables such as raw materials, labour, and expenses. Thus, for infrastructure projects as well, at the time of estimation of cost, these variables would come into play. The factors affecting cost for a public-private partnership project could be the following:

 

                        Illustration III: Factors affecting Cost of Projects: PPP model projects

FACTORS AFFECTING COST OF PROJECTS : PPP MODEL PROJECTS

Materials

Labour

Consultants

Contractor

Client

External
Factors

Dispute
Resolution

Costs and delays
associated with procurement and delivery of materials, import costs

Availability or non –
availability of skilled labour.

Recurring changes in
design

Poor site management
and supervision

Change orders

Force Majeure events
and weather changes.

International dispute
resolution in outside jurisdictions[1]

Unavailability of raw
materials

Poor management of
labour

Delay in approvals and
inspections

Inept subcontractors

Political and policy
changes such as MII[2]

Approvals from
authorities

Costly and time-consuming
domestic litigation

Wastage and theft of
materials – 13 to 14 million construction waste (FY 2000-2001)[3]

Increasing cost of
labour

Inaccuracy in design,
costs associated with knowledge transfer

Poor planning,
scheduling and cash flow management by Contractors

Poor communication for
quality and cost

Accidents

High legal costs and high
arbitrators fees[4].
Non-realisation of arbitral awards and court decree amounts.

 

 

Case Study: The Mumbai Monorail – An EPC Contract Model

 

Time and cost overruns in projects lead to disputes and arbitrations. A suitable example is the  Mumbai Monorail which has entered disputes and arbitration between the Contractor and the Authority over its project cost[9]. The development authority MMRDA entered into a contract with L&T Scomi Engineering for the construction of the Mumbai Monorail project. The original project cost between the Private Party Investors and the Authority was estimated to be Rs 2,700 crore, after which disputes arose. The Authority had claims against the Contractor for not completing the project task on time. The arguments of the Contractor pertained to the cost escalations caused by delays due to the fault of the Authority.  In 2019, the Bombay High Court appointed an arbitrator to settle the dispute. Currently, the dispute is still in the arbitration stage. Furthermore, post-December 2018, the MMRDA had taken over the Operation and Maintenance of the Mumbai Monorail project from L&T Scomi Engineering. Due to the Make in India policy, the tenders for manufacturing of the Mumbai Monorail were altered to encourage manufacturers and Indian technology partners to participate and fulfil the demands of manufacturing the additional monorail rakes[10]. Among other issues currently plaguing the Mumbai Monorail project, such as unavailability of a sufficient number of rakes to keep the services running and an inadequate number of spare parts, the widening deficit between revenue and O&M costs, remains primary.   

   

Way Forward

 

As per the report by the Ministry of Statistics cited above, the reason for cost and time overruns can be largely attributed to the state-wise lockdown due to the COVID-19 pandemic, which has been causing great hindrance to the implementation of infrastructure projects. Time and cost overruns in projects lead to disputes and arbitrations. Furthermore, in the procurement stage of projects, biddings in India happen with the project sponsor underbidding for the project so as to survive the competitive market. However, the underbidding combined with lack of margin included in the overall costs by contractors or sponsors often overlook inevitable hidden and unforeseeable costs which in turn enhance the final costs of the project. For instance, the Mumbai-Monorail project is a classic example of cost overrun. The solution would be to have a clear understanding of the project agreements, risks involved in the project particularly the conditions of force majeure, an objective evaluation of project cost while bidding taking into account uncertainties relating to raw material procurement, labour laws, land acquisition and risks related to cost and time overruns due to decisions of the awarding authority or public policy or any of the factors described above. The compensation clauses should be coherent and unambiguous, and in line with actual project cost incurred in the project leaving less scope for future disputes and arbitrations. Furthermore, it would be useful for the contractors / concessionaires , while making claims in an infrastructure project, to do it in a timely manner while maintaining clear and systematic evidentiary documentation, to substantiate the claims that may have arisen during the course of the project.

References: 

[1] http://www.cspm.gov.in/english/flr/FR_Mar_2021.pdf

[2] Finance Minister Smt. Nirmala Sitharaman releases Report of the Task Force on National Infrastructure Pipeline for 2019-2025, dated 31 December 2019, Press Information Bureau, pib.gov.in (2019), https://pib.gov.in/Pressreleaseshare.aspx?PRID=1598055 (last visited Sep 17, 2021).

[3] Forecasting Infrastructure Investment Needs and gaps, Global Infrastructure Outlook – A G20 INITIATIVE, https://outlook.gihub.org/ (last visited Sep 17, 2021).

[4] 422nd Flash Report on Central Sector Projects (Rs.150 Crore and Above), March 2021, Ministry of Statistics and Programme Implementation Infrastructure and Project Monitoring Division (2021), Available at: http://www.cspm.gov.in/english/flr/FR_Mar_2021.pdf (last visited Sep 17, 2021)

[5] Joseph Mante, Issaka Ndekugri & Nii Ankrah, Resolution of Disputes Arising From Major Infrastructure Projects In Developing Countries Fraunhofer, https://www.irbnet.de/daten/iconda/CIB_DC24504.pdf (last visited Sep 17, 2021).

[6] Make in India Initiative, Government of India.

[7] Sandeep Shrivastava and Abdol Chini M.E. Rinker Sr., Construction Materials and C&D Waste in India, School of Building Construction University of Florida, USA, https://www.irbnet.de/daten/iconda/CIB14286.pdf (last visited Sep 17, 2021).

[8] Amendments to the Arbitration and Conciliation Act, 1996, August 2014, Law Commission of India, Report No.246.

[9] Larsen and Toubro Limited Scomi Engineering BHD vs. Mumbai Metropolitan Region Development Authority MANU 2018 SC 1151, Arbitration Petition (C) No. 28 OF 2017.

[10]Adimulam, S. (2021, March 2). Mumbai: Monorail rakes will be made in India. Mumbai. Retrieved September 17, 2021, from https://www.freepressjournal.in/mumbai/mumbai-monorail-rakes-will-be-made-in-india.

 

 

Image Credits: Photo by Wade Austin Ellis on Unsplash

The solution would be to have a clear understanding of the project agreements, risks involved in the project particularly the conditions of force majeure, an objective evaluation of project cost while bidding taking into account uncertainties relating to raw material procurement, labour laws, land acquisition and risks related to cost and time overruns due to decisions of the awarding authority or public policy or any of the factors described above.